Coal-containing Wastewater Treatment System in Power Plant
A Coal-Containing Wastewater Reconstruction Project in Xinjiang
Abstract
Project Background
Original equipment: one set of chemical dosing system, one set of integrated coal water treatment equipment (processing capacity 8 tons/hour), and 7 water pumps.
Due to the large amount of coal powder in slime water, large amount of on-site reuse water, insufficient coal water treatment capacity, poor effluent quality, difficult reuse, inconvenient coal slime cleaning and other reasons, it is required to expand and transform the original coal water treatment equipment to improve the slime water treatment capacity to more than 30 tons/hour.

To achieve the effect

recommend Reading
Petrochemical coal-fired unit flue gas wet desulfurization wastewater treatment